Tracking subcontractor cost and forecast on a project

Subcontract cost is usually incurred well before it posts, so a project’s reported position can trail the work already done on site.

Foras keeps subcontractor cost against the same cost structure as everything else, so it reaches the position and the forecast rather than sitting to one side.

Northgate Logistics Park — Phase 2

Position · Aug 2026 · Demo data

Captured

£11.85m

Finance

£10.47m

Adjusted CTD

£11.97m

Illustrative Finance position by cost code, comparing captured project cost with Finance actuals, the difference, reconciliation adjustments, adjusted cost to date and the current position decision.
Cost codeCapturedFinanceDifferenceAdjustmentsAdjusted CTDDecision
150Project Management£1.84m£1.78m£60k£1.84mTiming
210Labour£2.96m£2.70m£262k£2.96m
311Shoring£1.43m£1.54m−£115k+£115k£1.54mMatch Finance
707Subcontract£3.18m£3.02m£158k£3.18m

Difference = Captured − Finance. A negative difference means captured cost sits below Finance. Shoring shows a Match Finance adjustment of +£115,000, so adjusted CTD equals the Finance position to date. Values rounded for display.

4 of 26 cost-code positions shownActual Foras interface pattern · Illustrative demo data

Why this is hard

A large cost stream that arrives late

Nothing about subcontract cost is simultaneous. The work, the recorded cost and the posting happen at different times, and the project has to hold a view across all three.

01

The cost is incurred long before it is posted

Work happens in week one, the cost is recorded against the project when it is known, and the invoice posts in a later period. The project carries a real cost for weeks with nothing in the ledger to show it.

02

Site knowledge and posted cost disagree

The site knows how many gangs were on, for how long, and what was disrupted. The ledger shows only what has reached it. Those are two different pictures of the same fortnight.

03

Subcontract cost is often held apart from the cost structure

When subcontract cost is kept in its own record rather than against the project cost structure, it has to be compared with Finance separately from everything else, on its own timetable.

04

Forecasting the remainder starts from an unclear base

Working out what remains means holding three things at once: the work done on site, the cost actually posted, and the scope still to run. When those sit in different places, the remaining cost is estimated rather than calculated.

How it usually goes

A side workbook, updated when the paperwork lands

Subcontract cost is commonly tracked in a workbook kept alongside the job, updated when invoices or statements arrive. It answers a commercial question well enough, but it is maintained separately from the project cost position.

Two problems follow. The same subcontract cost is represented differently in two places, so the reported position depends on which one you open. And the workbook is updated when documents arrive rather than as work happens, so the project’s view of subcontract cost trails both the ledger and what the site already knows.

The effect shows up at month end: subcontract is the line where the difference between captured cost and posted cost is largest, and the hardest to explain from records kept outside the cost position.

Northgate Logistics Park — Phase 2

Forecast lines · Cost Item view · Demo data

Illustrative forecast lines showing approved budget, raw cost to date, reconciliation adjustments, adjusted cost to date, remaining quantity, rate and utilisation, forecast cost to complete, forecast final cost and variance against approved budget.
Cost itemApproved budgetAdj CTDForecast CTCForecast final costVariance
210Direct labour£4,200,000£2,964,800£1,405,050£4,369,850£169,850 over
311Piling & shoring£1,900,000£1,541,700£336,000£1,877,700£22,300 under
707Drainage subcontract£3,600,000£3,180,500£520,000£3,700,500£100,500 over
Project total (all lines)£18,420,000£11,964,300£6,941,100£18,905,400£485,400 over
Actual Foras interface pattern · Illustrative demo data

Actual Foras interface pattern. Figures are illustrative demo data from the Northgate Logistics Park demo project.

How Foras handles it

Subcontract cost inside the position, not beside it

A subcontractor area, not a spreadsheet tab

Subcontractor records are maintained inside the project rather than in a side workbook, alongside the material supply and management cost areas.

Associated with the project cost structure

Subcontractor cost is associated with the project cost structure and Budget lines, so it sits in the same position as diary-captured labour, plant and materials.

Compared against posted Finance actuals

Where a subcontract cost has been posted, it appears in the Finance comparison per cost code with a recorded decision for any difference — Timing, or Match Finance.

Carried into the forecast

Subcontract cost forms part of adjusted cost to date, and the remaining work is forecast on its cost lines like any other cost stream — quantity, rate and utilisation.

Foras is a cost-control record, not a subcontract administration or payment system. It does not run valuations, assess applications, issue certificates, make payments or manage package final accounts. Finance remains authoritative for what has been posted.

What changes in practice

Month to month

The lag becomes visible instead of invisible

Work recorded but not yet posted shows as a difference with a decision attached, rather than as a gap nobody has quantified.

Subcontract cost sits on the same codes as everything else

Because subcontract cost is attributed to the project cost structure, it appears against the same cost codes as diary-captured labour, plant and materials rather than in a separate report.

The forecast has the same lineage as everything else

Subcontract cost to complete is built from the same reconciled position as the rest of the job, so the total forecast can be defended as one number.

Cost recorded but not yet posted is stated, not assumed

Where captured subcontract cost has not reached the ledger, it shows as a difference against Finance with a recorded decision, rather than as a gap somebody has to remember.