Foras compares the project cost position against imported Finance actuals per cost code, and keeps a recorded decision — with a reason and an author — behind every difference.

Northgate Logistics Park — Phase 2

Position · Aug 2026 · Demo data

Captured

£11.85m

Finance

£10.47m

Adjusted CTD

£11.97m

Illustrative Finance position by cost code, comparing captured project cost with Finance actuals, the difference, reconciliation adjustments, adjusted cost to date and the current position decision.
Cost codeDiffCTDDecision
150Project Management£60k£1.84mTiming
210Labour£262k£2.96m
311Shoring−£115k£1.54mMatch Finance
707Subcontract£158k£3.18m

Difference = Captured − Finance. A negative difference means captured cost sits below Finance. Shoring shows a Match Finance adjustment of +£115,000, so adjusted CTD equals the Finance position to date. Values rounded for display.

4 of 26 cost-code positions shownActual Foras interface pattern · Illustrative demo data

Why the gap persists

The difference is usually legitimate — and usually undocumented

Timing, coding and late postings all produce real differences. The problem is that the reasoning behind them is rarely captured anywhere durable.

01

Two numbers, no agreed explanation

The delivery team reports one cost position and the ledger shows another. The gap is usually real and usually explainable, but the explanation is not written down anywhere.

02

Accruals are estimated late and loosely

Work done but not yet invoiced is often a judgement made at close, without a dated record of the activity underneath it.

03

Reconciliation lives in someone's head

The person who worked out why the difference exists moves on, and next period the same analysis is done again from scratch.

04

Late postings reopen closed conversations

An invoice arrives after the delivery team has reported, and there is no clean way to show whether it was already anticipated.

How Foras helps

A reconciliation that is kept, not repeated

Finance stays authoritative

Posted actuals are imported from Finance and treated as the system of record. Foras does not post to your ERP and does not attempt to replace it.

Difference shown per cost code

Captured project cost sits beside imported Finance actuals so the difference is visible at code level rather than as one project-level number.

A recorded decision on each difference

Differences are settled with a decision such as Timing or Match Finance, carrying an adjustment, a reason and an author.

Adjusted cost to date as the agreed figure

Adjusted cost to date is captured cost plus recorded adjustments. It is the figure the delivery team reports and the one Finance can trace.

Dated site activity behind the position

Cost is captured against the day the work occurred, which gives the accrual conversation an underlying record rather than a round-number estimate.

The audit trail

Every adjustment carries a reason and an author

Reconciliation history stays with the project, so the explanation survives the person who produced it.

Position decision history

Aug 2026 · Demo data

  • 311 Shoring · WBS 02.10 Retaining Walls

    Match Finance
    Captured TD
    £812,400
    Finance TD
    £927,400
    Difference TD
    −£115,000
    Adjustment
    +£115,000
    Adjusted CTD
    £927,400

    Decided by Commercial Manager · 28 Aug 2026

  • 150 Project Management

    Timing
    Captured TD
    £1,842,300
    Finance TD
    £1,781,900
    Difference TD
    £60,400
    Adjustment
    No adjustment
    Adjusted CTD
    £1,842,300

    Decided by Commercial Manager · 28 Aug 2026

Superseded decisions remain in history rather than being removed. Actual Foras interface pattern · Illustrative demo data

Actual Foras interface pattern. Entries are illustrative demo data from the Northgate Logistics Park demo project.

What changes in practice

The month-end conversation

  1. 01

    Import posted actuals

    Finance actuals are brought in from COINS. This is an import and reconciliation workflow, not a real-time two-way integration.

  2. 02

    Compare against captured cost

    Differences surface per cost code as soon as the import lands, before anyone has written a report from either number.

  3. 03

    Record the decision

    Timing where the cost is real but not yet posted, Match Finance where Finance is correct and the project position should follow it.

  4. 04

    Keep the history

    Each adjustment retains its reason and author, so the same reconciliation is not re-derived next period.

What Foras is — and is not

Clear boundaries with your finance stack

No write-back to your ERP

Foras reads imported actuals and reconciles against them. Nothing Foras records posts into COINS or any other accounting system.

Not an accounting system

Foras is project controls, not a ledger. It does not perform accounting treatment, journals or statutory reporting.

Import, not real-time sync

Finance data arrives through import. Any claim of live bidirectional integration would be inaccurate, so we do not make one.

Bring one closed period. We’ll reconcile it in front of you.